The challenge
Warby-Ovens National Park lies at alpine foothills in Victoria, 240km northeast of Melbourne. The park provides an important connection between the forested mountains and nearby Murray River and floodplain.
In 2012, two access points into the national park were damaged by floods. Rather than simply repairing these accesses, the North East Catchment Management Authority saw an opportunity to also improve the waterway for fish passage.
The old crossings had been a barrier to fish migration. The new plans for vehicle access needed to:
- improve fish passage and floodplain connectivity at low flows
- minimise alteration to flow characteristics, while also minimising maintenance requirements and the potential for erosion.
Scope:
Design and construction of fishway passages and vehicle access on the Ovens River
Location:
Warby-Ovens National Park Victoria
Client:
North East Catchment Management Authority
Our solution
Water Technology worked in conjunction with Gordon Gibson Nominees and the Arthur Rylah Institute to:
- prepare detailed design plans for the fishways
- obtain relevant approvals
- construct the crossings to allow fish passage.
We consulted carefully with North East Catchment Management Authority and Parks Victoria to ensure the design was robust and fit for purpose.
Managing salinity is one of the most significant environmental challenges facing the basin.